From new dams and energy sources to expanded road networks and mining ventures, these initiatives are critical to the nation’s long-term stability and growth. Here’s an overview of the most important projects slated for completion or expansion onwards.
For the macro picture — GDP growth, sector breakdown, mineral wealth, and foreign investment flows — see our Afghanistan Economy & GDP guide →
📋 Project Overview — 2024 to 2027
Energy
CASA-1000 Power Transmission
In Progress2016 → 2026
1,300 MW HVDC line from Central Asia through Kabul. 75% of Afghan section complete as of late 2025.
Gas Pipeline
TAPI Gas Pipeline (Afghan Section)
In Progress2024 → 2027
$10B, 1,814 km pipeline. Afghan construction started Sep 2024. Herat completion target: end 2026.
Water / Agriculture
Qosh Tepa Canal
In Progress2022 → 2026
285 km canal diverting Amu Darya water to 550,000 ha. Phase 2 was 90% done by Dec 2024.
Railway
Khaf–Herat Railway (Section 4)
In Progress2024 → 2026
Final 86 km section into Herat city restarted Sep 2024. Full completion target: March 2026.
Railway
Torghundi–Herat–Kandahar Rail Corridor
In Progress2024 → 2027+
$40M first segment started Sep 2024. Kazakhstan signed $500M deal Jul 2025. Full corridor planned.
Mining
Mes Aynak Copper Mine
In Progress2024 → 2026
Access road inaugurated Jul 2024. World’s 2nd largest copper deposit. Contract renegotiation ongoing.
Dam / Irrigation
Kamal Khan Dam — Phase 3
Completed2017 → Feb 2025
Final phase inaugurated Feb 2025. 9 MW power + 175,000 ha irrigation in Nimruz Province.
Railway
Chabahar–Zahedan Railway
In Progress2016 → 2027
Iran’s Indian Ocean gateway to Afghan border. 84% complete Oct 2025; operations target Jun 2027.
Trade Corridor
UAP Railway Feasibility Study
In Progress2026 → 2027
Uzbekistan–Afghanistan–Pakistan rail. Feasibility study formally launched Feb 2026 by Uzbek president.
Railway
Herat–Mazar-i-Sharif Railway
Study Phase2025 → 2028+
$10M feasibility study agreed Oct 2025. $264M design contract for Kandahar–Herat signed Feb 2025.
Road
National Road Infrastructure Expansion
In Progress2024 → 2026
New trade routes to Tajikistan, Pakistan and border regions. Key routes expected complete by 2026.
Energy
Renewable Energy Initiatives
In Progress2024 → 2026
Solar farms, wind installations and upgraded hydroelectric plants across rural and urban Afghanistan.
Mining
Aynak Copper Mine Operationalisation
In Progress2024 → 2026
One of the world’s largest copper deposits in Logar Province. Full-scale extraction phase being prepared.
Water / Energy
Kajaki & Sultan Dam Upgrades
In Progress2024 → 2026
Major capacity upgrades for power generation and irrigation reach across southern Afghanistan.
Urban / Kabul
Kabul City Ring Road (95 km)
In Progress2024 → 2026
95 km ring road around Kabul to ease congestion and connect major districts. Commerce boost expected.
Urban / Kabul
Kabul Water & Waste Management
In Progress2024 → 2025
Upgraded water distribution and modern waste treatment systems for Kabul’s growing population.
Trade
Industrial & Agricultural Development Zones
In Progress2024 → 2026
Industrial and agricultural hubs with modern irrigation and manufacturing facilities to attract investment.
Sector:
Water
Energy
Rail
Road
Mining
Trade
Urban
Gas
Status:
✓ Completed
⚡ In Progress
🔬 Study Phase
2026
UAP Railway Feasibility Study Launched
February 2026 — Uzbekistan’s President Mirziyoyev formally decreed the launch of a joint feasibility study for the Uzbekistan–Afghanistan–Pakistan railway, one of the most transformative regional rail proposals in Eurasian history.
RailStudy Phase
2026
Chabahar–Zahedan Railway — Substructure 96% Complete
January 2026 — Iranian officials confirmed substructure 96% done, track laying 75% complete. Full construction expected end of 2026; railway operations target June 2027. Station buildings near completion.
RailIn Progress
2025
CASA-1000 — Converter Stations Complete; Afghan Section 75%
April 2025 — HVDC converter stations in Kyrgyzstan and Tajikistan completed. 485 km AC line between Datka and Khujand laid. Afghan section 75% done as of late 2025. Full project completion target: end 2026.
EnergyIn Progress
2025
Kazakhstan Signs $500M Herat–Torghundi Railway Deal
July 2025 — Kazakhstan’s Foreign Minister signed a $500 million agreement in Kabul in support of the 115–120 km Herat–Torghundi railway line, a crucial first section of the future north–south corridor.
RailIn Progress
2025
Kamal Khan Dam — Phase 3 Inaugurated
February 2025 — The final third phase of the Kamal Khan Dam in Nimruz Province was officially completed and inaugurated, delivering full irrigation coverage to ~175,000 hectares and 9 MW of hydroelectric power.
Water✓ Completed
2025
Herat–Mazar-i-Sharif Railway — $264M Design Contract Signed
February 2025 — A $264 million design contract for the Kandahar–Herat railway section was signed, advancing Afghanistan’s long-term north–south rail spine connecting its two major western cities.
RailStudy Phase
2025
Afghanistan–Turkmenistan MoUs: Railway Expansions
Late February 2025 — Multiple MoUs signed covering expansion of Torghundi station, completion of the Aqina–Andkhoy section, continuation of the 22 km Torghundi–Sangbar section, and feasibility study for the 55 km Andkhoy–Sheberghan railway.
RailIn Progress
2025
Khaf–Herat Railway — Completion Target March 2026 Confirmed
April 2025 — Iranian officials officially confirmed the 225 km Khaf–Herat railway is targeted for full completion by March 2026, with work advancing simultaneously on section 4 (Rozanak to Herat).
RailIn Progress
2025
TAPI Pipeline — Active Construction Through Herat Province
Early 2025 — TAPI pipeline construction continued through winter in Herat Province. Turkmenistan aims to deliver gas supplies to Afghanistan by 2027. Kazakhstan expressed interest in joining with a 30% stake (November 2025).
GasIn Progress
2025
Mes Aynak Mine — Infrastructure Development Continues
2025 — Following the July 2024 road inauguration, infrastructure preparatory works continued at Mes Aynak. Contract renegotiation with MCC and plans for a dedicated railway link to Kabul remain active agenda items.
MiningIn Progress
2024
TAPI Pipeline — Afghan Section Construction Begins
September 2024 — Construction officially started on the Afghan section of the TAPI gas pipeline near the Turkmenistan–Afghanistan border. Turkmen Foreign Minister Meredow confirmed readiness to begin work after meeting with Deputy PM Baradar in August 2024.
GasMilestone
2024
Torghundi–Sangbor Railway Section — $40M Construction Starts
September 2024 — A $40 million project began to extend the Turkmenistan–Afghanistan railway southward from Torghundi toward Sangbor, the first segment of the larger Torghundi–Herat–Kandahar corridor.
RailMilestone
2024
Khaf–Herat Railway — Section 4 Construction Resumes
September 2024 — Work resumed on the final 86 km section of the Khaf–Herat railway running from Rozanak to Herat’s industrial zone near the international airport, simultaneously with the Torghundi–Herat rail start.
RailIn Progress
2024
Mes Aynak Mine Road — Officially Inaugurated
July 2024 — The access road to the Mes Aynak copper mine was formally inaugurated by the Islamic Emirate, marking the start of preparatory infrastructure for one of the world’s largest untapped copper deposits worth tens of billions of dollars.
MiningMilestone
2024
China–Afghanistan Rail Freight via Iran — First Shipment Arrives
December 2024 — The first shipment of Chinese goods arrived in Afghanistan via Iran’s railway network, marking a historic milestone in Afghanistan’s integration into the China–Iran trade corridor and demonstrating the Khaf–Herat route’s commercial potential.
RailMilestone
2024
Qosh Tepa Canal — Phase 2 Reaches 90% Completion
December 2024 — Phase 2 of the 285 km Qosh Tepa Canal reached 90% completion, following Phase 1’s completion in October 2023. The canal, once fully operational, will irrigate 550,000 hectares of previously arid northern Afghan land.
WaterIn Progress
2024
TAT Railway Feasibility Study — Approved (KOICA Funding)
July 2024 — A KOICA-funded feasibility study for the Tajik section of the Turkmenistan–Afghanistan–Tajikistan (TAT) Railway was formally approved, covering a 51 km route with 28 bridges and 160 drainage systems, at a study cost of $4 million.
RailStudy Phase
New & Expanded Development Projects (2024–2026)
Beyond the flagship national and Kabul projects, a new wave of large-scale infrastructure, energy, and trade initiatives has moved from planning to active construction across Afghanistan since 2024. From transcontinental pipelines and railway corridors to massive canal and mining projects, these developments are reshaping the country’s economic geography and its links to the wider region.
1. Qosh Tepa Canal – Turning Desert into Farmland
The Qosh Tepa Canal is one of the most ambitious engineering undertakings in Afghan history. Stretching 285 km through the northern provinces of Balkh, Jowzjan, and Faryab, it diverts water from the Amu Darya to transform up to 550,000 hectares of arid desert into irrigated farmland. Construction began in 2022, Phase 1 was completed in October 2023, and by December 2024 Phase 2 was 90% complete.
Goals from 2024 Onwards: Complete Phase 2 and begin Phase 3; establish functioning irrigation systems for large-scale crop production in northern Afghanistan.
Importance: The canal could increase Afghanistan’s cultivated land by a third, dramatically boosting food security and agricultural exports in one of the country’s most underdeveloped regions.
Achievements Expected by 2026: Full operation of phases 1 and 2, delivering water to hundreds of thousands of hectares and supporting the livelihoods of communities across three northern provinces.
2. TAPI Gas Pipeline – Bringing Central Asian Energy to South Asia
The Turkmenistan–Afghanistan–Pakistan–India (TAPI) Pipeline is a $10 billion, 1,814 km natural gas pipeline running from the vast Galkynysh gas field in Turkmenistan through Herat and Kandahar in Afghanistan, then on to Pakistan and India. After years of delays, Afghanistan’s section officially began construction in September 2024. By early 2026, work was actively progressing through Herat Province, with completion to Herat city targeted by end of 2026.
Goals from 2024 Onwards: Complete the Afghan section of the pipeline alongside the Kandahar–Herat Highway corridor, enabling natural gas transit and providing up to 5 billion cubic metres of gas annually to Afghanistan itself.
Importance: TAPI will give Afghanistan a reliable domestic gas supply while generating significant transit revenues — a transformative step for energy independence and economic growth.
Achievements Expected by 2026–2027: Completion of the Afghan section to Herat; first gas deliveries to Afghan consumers projected once the full route to Pakistan is operational.
3. CASA-1000 Power Transmission Project
The Central Asia–South Asia Power Project (CASA-1000) is a $1.2 billion electricity transmission initiative connecting the hydroelectric surplus of Kyrgyzstan and Tajikistan to Afghanistan and Pakistan. A 750 km high-voltage direct current (HVDC) line runs through Kabul carrying up to 1,300 MW of electricity in total — Afghanistan’s initial allocation is up to 300 MW. By April 2025, the converter stations in Central Asia were complete, and as of late 2025, approximately 75% of the Afghan section had been finished.
Goals from 2024 Onwards: Complete the remaining Afghan section of the HVDC line, connect it to Kabul’s grid, and allow Afghanistan to draw up to 300 MW of additional power from the existing 220 kV Tajikistan–Afghanistan line.
Importance: Afghanistan suffers chronic electricity shortages. CASA-1000 will significantly increase available power for homes, businesses, and industry — particularly in Kabul — reducing dependency on expensive diesel generators.
Achievements Expected by 2026: Full project completion and commencement of electricity imports, providing a stable, affordable power source for millions of Afghans.
4. Khaf–Herat Railway – Connecting Afghanistan to Iran and Europe
The Khaf–Herat Railway is a 225 km standard-gauge line linking Khaf in eastern Iran to the city of Herat, with 140 km of track running through Afghan territory. Freight operations began in July 2023, and in September 2024 work resumed on the critical fourth and final section connecting Rozanak to Herat’s industrial zone near the airport. Iranian officials confirmed in April 2025 that the full line is targeted for completion by March 2026.
Goals from 2024 Onwards: Complete the fourth section of track into Herat; initiate passenger services between Mashhad and Herat; expand station capacity to handle increased cargo volume.
Importance: Completion of this railway will plug Afghanistan into the broader Eurasian rail network via Iran, enabling direct freight links to Turkey and European markets — and providing an alternative trade route that reduces dependency on Pakistani ports.
Achievements Expected by 2026: A fully operational rail corridor between Herat and Iran, with growing cargo volumes and the launch of the first scheduled passenger service between Mashhad and Herat.
5. Torghundi–Herat–Kandahar Railway Corridor
In September 2024, a $40 million project began to extend the Turkmenistan–Afghanistan railway southward from Torghundi toward Herat. This is the first phase of a far larger ambition: a railway running from Torghundi through Herat, Kandahar, and on to Spin Boldak at the Pakistani border. In April 2025, Afghanistan, Turkmenistan, and Kazakhstan signed a protocol of intent for this full corridor, and in July 2025 Kazakhstan’s foreign minister signed a $500 million deal in Kabul supporting the 115–120 km Herat–Torghundi section.
Goals from 2024 Onwards: Construct the initial Torghundi–Sangbor segment, advance feasibility studies for the Herat–Kandahar extension, and integrate fibre-optic communications and dry-port logistics along the route.
Importance: A north–south rail spine would fundamentally transform Afghanistan’s role as a transit hub, connecting Central Asian landlocked nations to South Asian markets through Afghan territory.
Achievements Expected by 2026–2027: Completion of the Torghundi–Sangbor section and commencement of construction on the longer Herat–Kandahar segment, laying the groundwork for Afghanistan’s future as a regional trade corridor.
6. Mes Aynak Copper Mine – Jumpstarting the Mining Sector
The Mes Aynak copper mine in Logar Province, awarded to China Metallurgical Group (MCC) under a 30-year lease, holds an estimated six million tonnes of copper — one of the largest untapped deposits on Earth. After more than a decade of delays, a significant milestone was reached in July 2024 when the road to the mine was formally inaugurated, signalling the start of serious preparatory infrastructure work.
Goals from 2024 Onwards: Complete access roads and supporting infrastructure; advance negotiations on revised mining contracts; begin preparatory earthworks and site development for eventual full-scale extraction.
Importance: Afghanistan’s mineral wealth is estimated at over $1 trillion. Mes Aynak alone could generate tens of billions of dollars in revenue, create thousands of jobs, and fund generations of public investment if properly developed.
Achievements Expected by 2026: Finalisation of the updated mining contract, completion of site access infrastructure, and the commencement of initial extraction activities — marking the real beginning of Afghanistan’s mining economy. Planning a visit? Read our Mes Aynak day-trip guide →
7. Kamal Khan Dam – Phase 3 and Expanded Irrigation
The Kamal Khan Dam on the Helmand River in Nimruz Province completed its long-awaited third and final phase in February 2025. The dam provides up to 9 MW of hydroelectric power and, crucially, delivers irrigation water to approximately 175,000 hectares of agricultural land in the arid southwest of Afghanistan — one of the country’s most underdeveloped regions.
Goals from 2025 Onwards: Maximise irrigation coverage across Nimruz and Helmand provinces; expand the canal network to bring water to additional farmland; increase power output through improved turbine efficiency.
Importance: Nimruz Province borders both Iran and Pakistan and has historically suffered from extreme drought and underdevelopment. Kamal Khan is central to the region’s agricultural revival and economic integration.
Achievements Expected by 2026: Full operational capacity of all three phases delivering water and power across southwestern Afghanistan, supporting food security and reducing out-migration from the region.
8. Chabahar–Zahedan Railway – Afghanistan’s Gateway to the Indian Ocean
While not inside Afghanistan, the Chabahar–Zahedan Railway in Iran is a critical piece of infrastructure for Afghan trade. When completed, it will link the deep-water port of Chabahar on the Gulf of Oman to the Afghan border at Zaranj, giving Afghanistan its first practical Indian Ocean trade route outside Pakistani territory. By late October 2025, the project was 84% complete; by January 2026 the substructure was 96% done, with full construction expected by end of 2026 and operations beginning in June 2027.
Goals from 2025 Onwards: Complete track laying and station construction; link the Zahedan terminal to the Afghan border town of Zaranj; develop complementary dry-port and customs infrastructure on the Afghan side.
Importance: Chabahar gives Afghanistan a sanctions-compliant, Indian Ocean–facing trade corridor, reducing reliance on Karachi and opening direct shipping routes to India, East Africa, and beyond.
Achievements Expected by 2027: A fully operational rail link from Chabahar port to the Afghan border, with freight volumes expected to grow rapidly as Afghan exporters gain access to new global markets.
9. Uzbekistan–Afghanistan–Pakistan (UAP) Railway Feasibility Study
In February 2026, Uzbekistan’s President Shavkat Mirziyoyev formally decreed the launch of a joint feasibility study on the Uzbekistan–Afghanistan–Pakistan (UAP) Railway — a proposed line that would run from Uzbekistan south through Afghanistan to Pakistan’s port cities, potentially giving Central Asia its most direct access ever to warm-water ports. The study involves the governments of all three nations and reflects growing geopolitical momentum behind Afghanistan’s role as a north–south transit corridor.
Goals from 2026 Onwards: Complete the technical and economic feasibility study; identify a preferred route through Afghan territory; secure multilateral financing commitments from development banks and regional funds.
Importance: The UAP railway would be one of the most transformative infrastructure projects in Eurasian history, potentially generating billions in annual transit revenues for Afghanistan and integrating the country into the heart of a new Silk Road network.
Achievements Expected by 2027: Completion of the feasibility study and announcement of the selected route, with construction financing negotiations underway among regional partners.
10. Herat–Mazar-i-Sharif Railway – The North–South Spine
The proposed Herat–Mazar-i-Sharif Railway, running roughly 800 km across northern Afghanistan, would for the first time connect the country’s two major western cities by rail. Uzbekistan has pledged co-financing, and in October 2025 Afghan, Iranian, and Turkish officials agreed to a $10 million feasibility study under the UN’s FNRC framework, with completion expected by March 2026. A $264 million design contract for the Kandahar–Herat section was also signed in February 2025.
Goals from 2025 Onwards: Complete the feasibility and engineering design studies; secure multilateral financing; begin preparatory construction works on the first segments connecting Herat eastward.
Importance: A continuous rail link across northern Afghanistan would unlock the mineral wealth of Jawzjan, Faryab, and Balkh provinces, integrate industrial and agricultural zones, and complete the missing link in the trans-Asian railway network connecting Europe to South and East Asia via Central Asia.
Achievements Expected by 2026: Finalisation of route designs and initiation of land acquisition for the first construction phase, with groundbreaking on pilot segments expected as financing is secured.